Description:

Project:

Construction and commissioning of the 70 kV Sanga-Ngombe Matadi HV line and the 70/30/15 kV – 7MVA substation at Ngombe Matadi are being carried out by Contractor the Ray Group Electromechanical.

Consistency of the work

  • Construction of a 70 kV line feeder unit at the NSANDA source substation.

These works consist of the supply, assembly and commissioning of electromechanical equipment HV 70kV

    • A line disconnector with MALT
    • A busbar disconnector
    • A 70kV HV circuit breaker
    • Three (3) Voltage transformer
    • Three (3) Current transformer
    • Three (3) line surge arrester
    • Supply and assembly of structures and electrical framework
    • Including civil works and earthing.
  1. Construction of a 70kV Nsanda- Gombe Matadi line 35 km long.

This work consists of:

    • Build the foundations of the pylons
    • Pylons erection
    • Addition of missing angles in the pylons
    • Pulling of the 70kV line
  1. Construction of the 70/30 / 15kV- 7 MVA GOMBE MATADI transformer station.

This work consists of:

    • Construction of a 70 kV incoming bay of the Nsanda substation
    • Construction of a transformer protection bay
    • Rehabilitation and maintenance of the 70/30 / 15kV- 7 MVA transformer

Mounting of the following electromechanical equipment;

  1. Mounting of one (1) 70kV HV circuit breaker
  2. Mounting of one (1) head-of-line disconnector
  3. Mounting of one (1) busbar disconnector
  4. Mounting of the 6 current transformers
  5. Mounting of the 6 voltage transformers
  6. Mounting of 6 70kV surge arresters
    • Civil engineering works and earth network of equipment
    • Construction of a control building and two houses of SNEL operators
    • Installation of the exterior lighting of the substation

Funding: SNEL

Region: DRC, Central Congo

Date: 2016 -2017